Service Interruption: September 29, 2024

When: Sunday, September 29, 2024, 06:00 AM to 06:00 PM


Where: Lima Estate including Rosewood, Palmdale,Sunnyvale and Campo Verde Subdivisions.


Why: The scheduled Power Interruption is initiated by NGCP for the following activities : 

a. General Maintenance & Testing of Batangas Limaland 69KV Line 1   associated HVES.

b. Preventive Maintenance of Main Protection.

c. Preventive Maintenance of SAS / Integrated MSBC & IED Meter. 


In relation to the above scenario, Lima EnerZone will take the oppurtunity to facilitate 

the activities below: 

a. Pole relocation located at Block 9  as per customer’s request.

b. 69 KV Pole Relocation located at Bugtong na Pulo, Lipa City

    as mandated  by DPWH.

c. Substation and OHDL Maintenances. 